Lead is negative lag: it lets the successor start before the dependency would otherwise allow, so the two tasks overlap. It is used to fast-track work that can begin on a partial output.

Lead is written with a minus sign: 1FS-3 means start three days before task 1 finishes. A designer can start laying out pages while the last of the copy is still being written.

Lead shortens the schedule but adds risk: the successor starts on an unfinished input, so rework becomes more likely if that input changes.

Worked example

TaskDurationDepends onScheduledTotal float
1. Write content10 daysNoneDays 1 to 100 days
2. Design layout5 days1FS-3Days 8 to 120 days

Write content runs to day 10. With a lead of 3 days, Design layout starts on day 8 instead of day 11, and the two tasks overlap.

Open this example in the free delay simulator to change the durations, the links or the delay and watch the schedule move.

Learn more

Related terms

Lag

Lag is a waiting time added to a dependency: the successor waits that many days after the link would otherwise allow it to start or finish.

Finish-to-start (FS)

A finish-to-start (FS) dependency means the successor cannot start until its predecessor has finished.

Critical path

The critical path is the longest chain of dependent tasks through a project.