Lead
Lead is negative lag: it lets the successor start before the dependency would otherwise allow, so the two tasks overlap. It is used to fast-track work that can begin on a partial output.
Lead is written with a minus sign: 1FS-3 means start three days before task 1 finishes. A designer can start laying out pages while the last of the copy is still being written.
Lead shortens the schedule but adds risk: the successor starts on an unfinished input, so rework becomes more likely if that input changes.
Worked example
| Task | Duration | Depends on | Scheduled | Total float |
|---|---|---|---|---|
| 1. Write content | 10 days | None | Days 1 to 10 | 0 days |
| 2. Design layout | 5 days | 1FS-3 | Days 8 to 12 | 0 days |
Write content runs to day 10. With a lead of 3 days, Design layout starts on day 8 instead of day 11, and the two tasks overlap.