Glossary

Project scheduling glossary

The terms behind every schedule, each defined in a sentence or two and shown on a small worked example calculated by Depentra's scheduling engine.

Dependencies

Project dependency

A project dependency is a link between two tasks that controls when one of them can start or finish, based on the other.

Predecessor and successor

In a project schedule, a predecessor is a task that another task depends on, and a successor is the task that depends on it.

Finish-to-start (FS)

A finish-to-start (FS) dependency means the successor cannot start until its predecessor has finished.

Start-to-start (SS)

A start-to-start (SS) dependency means the successor cannot start until its predecessor has started.

Finish-to-finish (FF)

A finish-to-finish (FF) dependency means the successor cannot finish until its predecessor has finished.

Start-to-finish (SF)

A start-to-finish (SF) dependency means the successor cannot finish until its predecessor has started.

Lag

Lag is a waiting time added to a dependency: the successor waits that many days after the link would otherwise allow it to start or finish.

Lead

Lead is negative lag: it lets the successor start before the dependency would otherwise allow, so the two tasks overlap.

Schedule analysis

Critical path

The critical path is the longest chain of dependent tasks through a project.

Total float

Total float, also called slack, is the number of days a task can slip without moving the project's finish date.

Free float

Free float is the number of days a task can slip without delaying the earliest start of any task that depends on it.

Delay propagation

Delay propagation is the way a delay on one task moves the tasks that depend on it, directly or through a chain, until slack in the plan absorbs it or it reaches the project's finish date.

Planning and control

Schedule baseline

A schedule baseline is a saved copy of the approved schedule, the dates a project committed to, that progress and forecasts are measured against.

Milestone

A milestone is a point in a schedule with no duration that marks an event, such as a sign-off, a delivery or a go-live, rather than a piece of work.

Cross-project dependency

A cross-project dependency is a link between tasks in two different projects, where work in one project waits on work in another.

Go deeper

The guides work the methods through by hand; the free simulator runs them on your own plan.