Glossary

Start-to-start (SS)

A start-to-start (SS) dependency means the successor cannot start until its predecessor has started. It lets two tasks run in parallel, often with a lag so the second begins a few days after the first.

SS suits work that can follow closely behind other work, such as validating data while it is still being migrated. It is written as 3SS, or 3SS+2 for a two-day lag.

Because the link only looks at the predecessor's start, a predecessor that starts on time but finishes late does not move an SS successor. That is a common surprise when people expect every link to pass a delay on.

Worked example

TaskDurationDepends onScheduledTotal floatAfter the delay
1. Data migration10 daysNoneDays 1 to 100 daysDays 1 to 14
2. Data validation8 days1SS+3Days 4 to 110 daysUnchanged

The delay: Data migration takes 4 days longer.

Data validation starts 3 days after Data migration starts, on day 4, and both run in parallel. If the migration takes 4 days longer, it finishes on day 14, but validation still starts on day 4: only a late start would move it.

Open this example in the free delay simulator to change the durations, the links or the delay and watch the schedule move.

Learn more

Related terms

Finish-to-start (FS)

A finish-to-start (FS) dependency means the successor cannot start until its predecessor has finished.

Finish-to-finish (FF)

A finish-to-finish (FF) dependency means the successor cannot finish until its predecessor has finished.

Lag

Lag is a waiting time added to a dependency: the successor waits that many days after the link would otherwise allow it to start or finish.

See it on your own plan

Depentra calculates every date, link and float in your plan and shows what moves when something slips.