Schedule baseline

A schedule baseline is a saved copy of the approved schedule, the dates a project committed to, that progress and forecasts are measured against. The gap between a baseline date and the current forecast is the schedule variance.

Without a baseline, a plan that has quietly slipped looks the same as one that was always meant to finish late. With one, every forecast date can be compared with what was promised.

Teams re-baseline when the scope or the agreed dates genuinely change, and keep the earlier baselines so the history of the changes stays visible.

Worked example

TaskDurationDepends onScheduledTotal floatAfter the delay
1. Requirements5 daysNoneDays 1 to 50 daysUnchanged
2. Build15 days1Days 6 to 200 daysDays 6 to 24
3. Testing5 days2Days 21 to 250 daysDays 25 to 29
4. Go-liveMilestone3Day 260 daysDay 30

The delay: Build takes 4 days longer.

The baseline has Go-live on day 26. After a slip of 4 days on Build, the forecast is day 30: a schedule variance of 4 days late.

Open this example in the free delay simulator to change the durations, the links or the delay and watch the schedule move.

Learn more

Related terms

Milestone

A milestone is a point in a schedule with no duration that marks an event, such as a sign-off, a delivery or a go-live, rather than a piece of work.

Delay propagation

Delay propagation is the way a delay on one task moves the tasks that depend on it, directly or through a chain, until slack in the plan absorbs it or it reaches the project's finish date.

Critical path

The critical path is the longest chain of dependent tasks through a project.