Saving and comparing baselines

How to save a baseline, what the variance columns mean, and how many baselines each plan allows.

What a baseline is

A baseline is a snapshot of the plan at a moment in time. Once saved it does not change, which is what makes it useful: it is the version you agreed to, preserved so you can measure drift against it.

Save one when a plan is signed off, not continuously. A baseline you re-save every week measures nothing.

Saving one

Open Baselines and choose to save a baseline now. You can give it a name, which is worth doing -- "Board sign-off, March" is easier to reason about later than a date.

Reading the variance

Once a baseline exists, each task shows its baseline start and end against its current dates, plus three variances: finish variance in days, effort variance, and cost variance.

Tasks created after a baseline was saved are marked as such rather than being shown with a nonsensical variance against dates that never existed.

You can also hide a baseline from the Gantt while keeping it saved, which is useful when you have several and only want to compare against one at a time.

Which plans have baselines

Baselines are a Professional feature, with up to 5 saved per project. When a project reaches 5, delete an old one to save a new one.

Related articles

Reading the Gantt chart and changing the timeline scale

Day, week, month, and year zoom levels, what each element on the chart means, and how to export the timeline.

Reading total float

What total float means, how Depentra calculates it, how to add the Float property and filter it, and why the numbers keep changing.

Still stuck?

If this did not answer your question, tell us what you were trying to do and we will help.