Timeline and scheduling

Working calendars, holidays and planned gaps

Count durations, lags and delays in working days, add holidays, and decide what a planned gap between linked tasks means.

Working days and holidays

Project settings, Scheduling: choose the days of the week that are working days and add holidays. Durations, lags, delays and float are then counted in working days, and no forecast lands on a day nobody works.

With no calendar every day is a working day, which is how every project counted before calendars existed. A task with no delay and nothing pushing it keeps its planned dates on any calendar.

Planned gaps

When the plan leaves a gap between two linked tasks, the project chooses what it means. Keep the gaps you planned (the default): a slip moves the next task by the same amount. Use planned gaps as slack: a slip uses up the gap before the next task moves.

Before you save, the page shows which tasks would move under the new settings.

Related articles

Reading the Gantt chart and changing the timeline scale

Day, week, month, and year zoom levels, what each element on the chart means, and how to export the timeline.

Creating dependencies, with lag and lead time

How to link tasks so one waits on another, how to add lag or lead time, and why circular chains are blocked.

Reading total float

What total float means, how Depentra calculates it, how to add the Float property and filter it, and why the numbers keep changing.